Pay Less Notice Adjudication for a Plumbing Subcontractor
The adjudicator awarded £424,189 plus interest and costs after the Pay Less Notice was served late.
- Client
- Plumbing sub-subcontractor
- Party representation
- Referring Party
- Issue
- The MEP subcontractor served its Pay Less Notice one day late and sought to resist payment by relying on an earlier true-value adjudication and contractual set-off provisions.
- ICRS involvement
- ICRS supported the plumbing sub-subcontractor in the adjudication and examined the Pay Less Notice timing, payment position and contractual payment mechanism.
- Deliverable
- Adjudication support and Pay Less Notice analysis.