Case Studies

Selected Construction Claims and Dispute Matters

ICRS Consult supports subcontractors, contractors, employers and professional teams on UK and international construction claims and disputes.

Our experience includes payment recovery, delay, disruption, quantum, contractual defence, adjudication, arbitration and expert support.

United Kingdom

UK Commercial and Dispute Matters

Selected UK matters involving payment recovery, delay, quantum, retained commercial support, contractual defence and construction disputes.

Payment Notices & Pay Less Notices

Matters involving payment notices, Pay Less Notices, notified sums and payment entitlement.

United Kingdom

Pay Less Notice Adjudication for a Plumbing Subcontractor

The adjudicator awarded £424,189 plus interest and costs after the Pay Less Notice was served late.

Client
Plumbing sub-subcontractor
Party representation
Referring Party
Issue
The MEP subcontractor served its Pay Less Notice one day late and sought to resist payment by relying on an earlier true-value adjudication and contractual set-off provisions.
ICRS involvement
ICRS supported the plumbing sub-subcontractor in the adjudication and examined the Pay Less Notice timing, payment position and contractual payment mechanism.
Deliverable
Adjudication support and Pay Less Notice analysis.
United Kingdom

Pay Less Notice Adjudication for a Drylining Subcontractor

The adjudication award was £176,418 plus interest after the main contractor’s notice argument failed.

Client
Drylining subcontractor
Party representation
Referring Party
Issue
The main contractor served a Payment Notice five days late and later argued that the document should instead be treated as a valid Pay Less Notice.
ICRS involvement
ICRS supported the drylining subcontractor in the adjudication and examined the payment notice position, notice timing and contractual payment mechanism.
Deliverable
Adjudication support and payment notice analysis.
United Kingdom

Payment Notice Recovery for an M&E Subcontractor

A payment notice strategy supported a £128,000 payment recovery for an M&E subcontractor.

Client
M&E subcontractor
Issue
Payment was withheld after a disputed interim application.
ICRS involvement
ICRS examined the payment application, contractual payment timetable, notice position and project records.
Deliverable
Payment notice analysis and payment recovery strategy.

Expert Reports

Quantum, delay and disruption expert work supporting construction disputes and adjudications.

United Kingdom

Delay and Disruption Expert Report for a Joinery Subcontractor

Delay and disruption expert report supports a £195,000 adjudication recovery for a joinery subcontractor.

Client
Joinery subcontractor
Issue
The subcontractor experienced delay, disrupted access, inefficient working and productivity loss.
ICRS involvement
Reviewed the delay and disruption events, productivity effects, project records and claimed loss.
Deliverable
Delay and disruption expert report.
United Kingdom

Quantum Expert Report for an M&E Subcontractor

Quantum expert report supports a £305,000 adjudication recovery for an M&E subcontractor.

Client
M&E subcontractor
Issue
The dispute concerned valuation, variations, deductions and payment entitlement.
ICRS involvement
Reviewed the valuation position, variation account, contra charges and supporting records.
Deliverable
Quantum expert report.
United Kingdom

Quantum Expert Report for a Civil Engineering Subcontractor

Quantum expert report supports a £416,000 adjudication recovery for a civil engineering subcontractor.

Client
Civil engineering subcontractor
Issue
The payment dispute concerned delay-related costs and disruption-related losses.
ICRS involvement
Reviewed payment items, deductions, cost records, overrun costs and disruption-related losses.
Deliverable
Quantum expert report.

Valuation, Final Account & Delay Adjudications

Adjudication matters involving valuation, final accounts, variations, delay and disruption.

United Kingdom

Final Account Adjudication for a Painting Subcontractor

The adjudicator awarded £184,000 and interest in the final account adjudication.

Client
Specialist painting and surface preparation subcontractor
Party representation
Referring Party
Issue
The final account dispute concerned original works, variations and other works.
ICRS involvement
ICRS examined the account, separated original scope from variations and represented the subcontractor through adjudication.
Deliverable
Referring Party representation, Notice of Adjudication, Referral, valuation analysis and evidence.
United Kingdom

Interim Valuation Adjudication for a Groundworks Subcontractor

Approximately £188,000 awarded in interim valuation adjudication.

Client
Specialist groundworks and civil engineering subcontractor
Party representation
Referring Party
Issue
The parties’ interim valuation positions differed by approximately £215,000, including disputed variations and additional works.
ICRS involvement
Strengthened the account’s substantiation and represented the subcontractor through Notice, Referral, Response analysis and Reply.
Deliverable
Referring Party representation, Notice of Adjudication, Referral, Reply and supporting adjudication bundle.
United Kingdom

Delay and Disruption Adjudication for a Cladding Subcontractor

Approximately 65% of the £2 million delay and disruption claim was dismissed.

Client
Major specialist cladding and curtain walling subcontractor
Party representation
Responding Party
Issue
The main contractor advanced a claim of approximately £2 million for alleged delay and disruption on a commercial office development.
ICRS involvement
Led the Responding Party defence, tested the retrospective delay analysis and coordinated the factual, programme, quantum and witness evidence.
Deliverable
Responding Party representation, Response, further submissions, witness evidence, expert coordination and adjudication meeting representation.

Commercial Retainers

Retained commercial support involving final accounts, variations and change, prolongation, liquidated damages, adjudication readiness and commercial settlement.

United Kingdom

Commercial Closeout Support for an MEP Subcontractor

£165,000 of liquidated damages exposure was avoided, £86,000 of prolongation costs was recovered, and disputed variations and the final account were settled commercially.

Client
MEP subcontractor
Issue
Commercial closeout involved disputed variations, unresolved prolongation recovery and potential exposure to liquidated damages.
ICRS involvement
ICRS provided seven months of retained advice on variation recovery, prolongation costs and the subcontractor's commercial position on liquidated damages.
Deliverable
Retained commercial advice on final account, variations, prolongation and liquidated damages exposure.
United Kingdom

Commercial Settlement of a £2.65 Million Change Dispute

The £2.65 million dispute was commercially settled at £2.15 million without proceeding to adjudication.

Client
Civil engineering subcontractor
Issue
A £2.65 million change remained disputed on a road infrastructure project and was at risk of proceeding to adjudication.
ICRS involvement
ICRS provided five months of retained advice on valuation methodology, alignment with subcontract requirements, adjudication readiness and settlement strategy.
Deliverable
Valuation strategy, adjudication readiness advice, contractual correspondence and settlement support.
United Kingdom

Final Account Settlement Under a Letter of Intent

The final account was agreed at £384,000 following an amicable settlement; the Letter of Intent had stated an £85,000 cap.

Client
Fit-out subcontractor
Issue
A final account dispute arose after the subcontractor substantially completed works under an £85,000 Letter of Intent, without an executed subcontract.
ICRS involvement
ICRS provided approximately six months of retained advice on the Letter of Intent, final account strategy, variation valuation and settlement.
Deliverable
Letter of Intent review, final account strategy, variation valuation advice, contractual correspondence and settlement agreement.

Commercial Recovery & Contractual Defence

Commercial matters involving retention recovery, contractual entitlement and defence of substantial claims.

United Kingdom

Retention Recovery for a Brickwork Subcontractor

The subcontractor secured a £82,500 retention recovery.

Client
Specialist brickwork subcontractor
Issue
Retention remained withheld after completion of the subcontract works.
ICRS involvement
ICRS examined the contractual arrangement, payment history, retention position and project records.
Deliverable
Retention recovery strategy and contractual correspondence.
United Kingdom

Contractual Defence to a Substantial Damage Claim

Contractual defence limited a £279,000 damages claim to a minimal commercial settlement.

Client
HVAC subcontractor
Issue
A substantial damages claim arose following an incident during the construction period.
ICRS involvement
Reviewed the subcontract, completion position, notice history and insurance provisions.
Deliverable
Contractual defence analysis and position paper.

AI Automation

AI automation matters involving tender pricing, contract issue review and factual chronology preparation for construction businesses.

United Kingdom

AI Tender Pricing Automation for an M&E Subcontractor

The workflow reduced manual first pass pricing and applied historic tender and cost data consistently across new BOQs.

Client
M&E subcontractor
Issue
Estimators manually applied historic cost and tender data when pricing new BOQs.
ICRS involvement
ICRS structured the client’s historic pricing and cost data and designed, tested and implemented the tender pricing workflow.
Deliverable
AI assisted BOQ pricing workflow with rate matching, pricing explanations, confidence controls and estimator review.
United Kingdom

AI Contract and Project Issue Review for a Façade Subcontractor

The workflow reduced manual record and contract review and provided the commercial team with traceable analysis to support subcontract administration and decisions.

Client
Façade subcontractor
Issue
Project issues required manual review of project records and amended subcontract terms to identify the supporting facts and governing subcontract provisions.
ICRS involvement
ICRS designed and implemented the complete review workflow, including record analysis, contract analysis, report structure, source referencing and recommendations.
Deliverable
AI assisted IRAC review workflow producing Issue, Rule, Analysis, Conclusion and Recommendations reports with source references.
United Kingdom

AI Factual Chronology Automation for a Civil Engineering Subcontractor

The workflow reduced the manual work required to prepare factual chronologies for claims, adjudications and contractual correspondence.

Client
Civil engineering subcontractor
Issue
Preparing factual chronologies for delay and disruption events required extensive manual review, referencing and collation of project records.
ICRS involvement
ICRS designed and implemented the complete workflow for event identification, record analysis, chronology preparation, source referencing and supporting document collation.
Deliverable
AI assisted factual chronology workflow producing formatted chronology reports with footnotes, document references, numbering and organised supporting records.
International

International Claims and Dispute Matters

Selected international matters involving arbitration, dispute boards, quantum, prolongation, acceleration, disruption and time and cost claims.

InternationalDubai, UAE

Quantum Expert, MEP Subcontract Arbitration, Healthcare Facility, Dubai

Appointment
Appointed as independent quantum expert in arbitration proceedings.
Issue
Disputed MEP quantum claims on a major healthcare and research facility in Dubai.
Deliverable
Independent quantum expert report addressing the valuation of the disputed MEP claims.
InternationalDubai, UAE

Dispute Adjudication Board Support, Metro Infrastructure Project, Dubai

Appointment
Engaged by a specialist MEP subcontractor to support a FIDIC DAB referral.
Issue
Prolongation and acceleration claims on a major Dubai metro infrastructure project.
Deliverable
Quantum reports for prolongation and acceleration claims submitted to the DAB.
InternationalDubai, UAE

Arbitration Claim Preparation, Major Hotel Development, Dubai

Appointment
Engaged by a joint venture to prepare and strengthen quantum claims for arbitration.
Issue
Substantial unresolved quantum on a major Dubai hotel development requiring properly prepared claims for arbitration.
Deliverable
Quantum claim submissions for arbitration, including valuation schedules, cost substantiation and supporting records analysis.
InternationalDubai, UAE

Subcontractor Disruption Claim, Major Hotel Project, Dubai

Appointment
Assisted the quantum expert as part of an expert team in arbitration proceedings.
Issue
Disputed disruption claim requiring an evidenced assessment of claimed lost labour hours.
Deliverable
Expert assessment of claimed lost labour hours in relation to a subcontractor disruption claim.
InternationalCanada

Additional Time and Cost Claim, Electrification Infrastructure Works, Canada

Appointment
Engaged by a contractor to prepare a claim for additional time and associated costs.
Issue
Time and cost impacts on a Canadian electrification infrastructure project requiring a properly substantiated claim submission.
Deliverable
Claim submission for additional time and associated costs, including contractual basis, time impact analysis and cost substantiation.

Discuss a construction claim or dispute

Speak to ICRS about the dispute, the contractual position and the supporting records.

The initial discussion is free of charge.

Contact

Send Us a Message

Just your name, email and a few lines about the issue. We will come back to you within 24 hours.